Sequence 1 and 2 will be performed concurrently to facilitate Pipeline replacement Phase 2 from Kennedale Balancing Reservoir to Mouser Way (anticipated to begin Summer 2027).

Phase 1 revised overview:

2026 February – July

  • Demo and removal of existing pipe between Mouser Way and Walnut Ridge Drive
  • Install new Steel Pipe starting east of Walnut Creek Drive proceeding east to Heritage Parkway
  • UPRR Tunnel near Heritage Parkway

2026 March – July

  • Mansfield Tunnels
    • Broad Street
    • Hobby Lobby parking lot/287 access road
  • Install new Steel Pipe starting at Heritage Parkway proceeding east to Walnut Ridge Drive
  • Surface and stream restoration starting east of Walnut Creek Drive proceeding east to Heritage Parkway

2026 August – September

  • Install new Steel Pipe starting at Mouser Way proceeding east to Walnut Creek Drive
  • Surface restoration starting at Mouser Way proceeding east to Walnut Creek Drive
Lake Current Level Conservation Level* Level Difference**
Arlington 548.51 550.00 -1.49
Benbrook 690.42 694.00 -3.58
Bridgeport 831.25 836.00 -4.75
Cedar Creek 318.14 322.00 -3.86
Eagle Mountain 646.61 649.10 -2.49
Lake Worth 592.44 594.00 -1.56
Richland-Chambers 313.13 315.00 -1.87

Want to add Lake Levels to your home screen? Click here to learn how

*Conservation Level: The permitted level of water an entity is allowed to hold in a lake. Any amount above the conservation level is used for the temporary storage of flood waters and must be released downstream.

**Difference: Amount above or below conservation level.

Stay connected with TRWD!

Sign up for our newsletter!

Newsletter Sign Up