6-Month Look-Ahead

The following is a 6-month estimate of activities.

Schedule is subject to change due to weather or adjustments to progress.

For future Pipeline projects visit our Capital Improvements blog:

https://www.trwd.com/category/pipeline-construction/

 

Jan:

Broad St tunnel

Jan-Feb:

Mansfield Marketplace tunnel

Walnut Creek tunnel

Walmart * to Walnut Creek

*

 

Feb:

Walnut Creek to Broad St

UPRR Mansfield tunnel to Low Branch Creek

US287 tunnel

Mar: 

Broad St to Mansfield Marketplace

Mansfield Marketplace to US287

Union Pacific Railroad (UPRR) Manfield tunnel

Mar-Apr:

Low Branch Creek to McKensie Middle School to Matlock Rd* to SH360 @ Lonestar Rd*

May: 

US287 to Mitchell Rd to UPRR Mansfield

SH 360 @ Lonestar Rd* to Hidden Hollow Dr to 2X12

 

*Indicates a temporary detour or road closure

Lake Current Level Conservation Level* Level Difference**
Arlington 549.60 550.00 -0.40
Benbrook 692.27 694.00 -1.73
Bridgeport 831.50 836.00 -4.50
Cedar Creek 318.69 322.00 -3.31
Eagle Mountain 647.09 649.10 -2.01
Lake Worth 592.18 594.00 -1.82
Richland-Chambers 312.86 315.00 -2.14

Want to add Lake Levels to your home screen? Click here to learn how

*Conservation Level: The permitted level of water an entity is allowed to hold in a lake. Any amount above the conservation level is used for the temporary storage of flood waters and must be released downstream.

**Difference: Amount above or below conservation level.

Stay connected with TRWD!

Sign up for our newsletter!

Newsletter Sign Up