Phase 1 overview:

Construction Progress is subject to changes due to weather and schedule. New or updated items are indicated in bold.

October 2026 – December 2026

  • Mansfield Tunnels
    • Walnut Creek Drive: Daily Apr 6-Oct 29 Tunneling & install casing.
    • Broad Street: Daily Oct 12 – Nov 13 Tunneling & install casing.
      • Daily Nov 16- Nov 25 Install new Steel Pipe within the casing.
    • Between Hobby Lobby parking lot and 287 access road: Daily Oct 26 – Nov 20 Tunneling & install casing.
      • Daily Nov 27- Dec 3 Install new Steel Pipe within the casing.
    • US287: Daily Dec 14- Jan 11 Install new Steel Pipe within existing US287 casing.
    • Walnut Creek: Daily Nov 2 – Dec 4 Tunneling & install casing.
  • UPRR Tunnel Mansfield
    • Daily Sept 21 – Nov 23: Removal of concrete pipe within existing UPRR casing.
    • Daily Nov 23 – Dec 15: Install new Steel Pipe within existing UPRR casing.
  • Surface and stream restoration Mouser Way to Walnut Ridge Drive.

December 2026 – March 2027

  • Surface and stream restoration Mouser Way to Walnut Ridge Drive.
  • Demo and removal of existing pipe between Walnut Ridge Drive and Hwy 667.
  • Install new Steel Pipe starting east of Walnut Ridge Dr proceeding east to FM661/Lakeview Dr.
  • Tunnels
    • FM661/Lakeview: Daily Feb 12- Mar 25 Tunneling & install casing.
Lake Current Level Conservation Level* Level Difference**

Want to add Lake Levels to your home screen? Click here to learn how

*Conservation Level: The permitted level of water an entity is allowed to hold in a lake. Any amount above the conservation level is used for the temporary storage of flood waters and must be released downstream.

**Difference: Amount above or below conservation level.