Phase 1 overview:

Construction Progress is subject to changes due to weather and schedule. New or updated items are indicated in bold.
February – July
- Demo and removal of existing pipe between Mouser Way and Walnut Ridge Drive
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way between Mouser Way and Walnut Creek.
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way west of UPRR Mansfield.
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way under Heritage Pkwy bridge.
- Install new Steel Pipe between Mouser Way and Walnut Ridge Drive
- Daily Apr 27-May 29: Install new Steel Pipe within the TRWD right-of-way between Mouser Way and Walnut Creek.
- Daily Apr 20-May 29: Install new Steel Pipe within the TRWD right-of-way west of UPRR Mansfield.
- Daily Apr 20-May 29 Install new Steel pipe within the TRWD right-of-way under Heritage Pkwy bridge.
- UPRR Tunnel Mansfield
- Daily Apr 20-May 29: Removal of concrete pipe within existing UPRR casing.
- Daily Apr 27-May 29: Install new Steel Pipe within UPRR Mansfield existing casing.
April – August
- Demo and removal of existing pipe between Heritage Pkwy and SH360:
- Daily May 4-June 30 Removal of concrete pipe within the TRWD right-of-way between Heritage Pkwy and River Birch Dr.
- Daily June 30-July 31 Removal of concrete pipe within the TRWD right-of-way between River Birch Dr. and SH 360.
- Install new Steel Pipe between Heritage Pkwy and SH 360
- Daily May 4-June 30 Install new Steel Pipe within the TRWD right-of-way between Heritage Pkwy and River Birch Dr.
- Daily June 30-July 31 Install new Steel Pipe within the TRWD right-of-way between River Birch Dr. and SH 360.
- Mansfield Tunnels
- Walnut Creek: Daily Apr 6-May 31 Tunneling & install Casing.
- Broad Street: Daily Apr 13-Jul 31 Tunneling & install Casing.
- Between Hobby Lobby parking lot and 287 access road: Daily Apr 20-Aug 28 Tunneling & install Casing within the TRWD right-of-way between the parking lot and US287 access road.
- US287: Daily Apr 20-May 29 Removal of concrete pipe within existing US287 casing.
- US287: Daily May 29-Aug 31 Install new Steel Pipe within existing US287 casing.
- Surface and stream restoration starting east of Walnut Creek Drive proceeding east to Heritage Parkway
August – September
- Surface restoration Mouser Way to US287
- Between SH 360 and Walnut Ridge Dr: Daily Aug 1-Sept 30 Removal of concrete pipe within the TRWD right-of-way.
- Between SH 360 and Walnut Ridge Dr: Daily Aug 1-Sept 30 Install new Steel Pipe within the TRWD right-of-way.