Phase 1 overview:

Construction Progress is subject to changes due to weather and schedule. New or updated items are indicated in bold.
2026 February – July
- Demo and removal of existing pipe between Mouser Way and Walnut Ridge Drive
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way between Mouser Way and Walnut Creek.
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way west of UPRR Mansfield.
- Daily Apr 13-May 29: Removal of concrete pipe within the TRWD right-of-way under Heritage Pkwy bridge.
- Install new Steel Pipe between Mouser Way and Walnut Ridge Drive
- Daily Apr 27-May 29: Install new Steel Pipe within the TRWD right-of-way between Mouser Way and Walnut Creek.
- Daily Apr 20-May 29: Install new Steel Pipe within the TRWD right-of-way west of UPRR Mansfield.
- Daily Apr 20-May 29 Install new Steel pipe within the TRWD right-of-way under Heritage Pkwy bridge.
- UPRR Tunnel Mansfield
- Daily Apr 20-May 29: Removal of concrete pipe within existing UPRR casing.
- Daily Apr 27-May 29: Install new Steel Pipe within UPRR Mansfield existing casing.
2026 April – August
- Walnut Creek: Daily Apr 6-May 31 Tunneling & install Casing.
- Broad Street: Daily Apr 13-Jul 31 Tunneling & install Casing.
- Between Hobby Lobby parking lot and 287 access road: Daily Apr 20-Aug 28 Tunneling & install Casing within the TRWD right-of-way between the parking lot and US287 access road.
- US287: Daily Apr 20-May 29 Removal of concrete pipe within existing US287 casing.
- US287: Daily May 29-Aug 31 Install new Steel Pipe within existing US287 casing.
- Surface and stream restoration starting east of Walnut Creek Drive proceeding east to Heritage Parkway
2026 August – September
- Surface restoration Mouser Way to US287